11 May 2022

PLOT 1000, OLDHAM: NEW DISTRIBUTION UNIT – STEEL FRAME AND CLADDING PROGRESSING

Approximately 50% of the steel frame has been progressed with cladding following close behind. As with many projects lead in for steel and cladding has caused programme anxiety as a result of the industry suffering from unprecedented demand and unprecedented price increases. The project team breathed a sigh of relief when the steel started to be delivered to site. Completion is targeted for the end of August and costs are forecast to be within the Budget. MAW Consulting are providing Quantity Surveying and Employers Agent Services